"Samarco currently expects to restart its operations around the end of 2020"

The shuttered Samarco iron ore operation in Brazil, jointly owned by Vale SA and BHP, has been licensed to restart at a reduced capacity.

Staff reporter
Samarco JV partners Vale and BHP have been licensed to restart the Germano complex in Brazil

Samarco JV partners Vale and BHP have been licensed to restart the Germano complex in Brazil

Samarco Mineração received the Corrective Operation Licence for the Germano complex in Minas Gerais on Friday, Vale said.

The operation has been closed since the deadly Samarco dam disaster in November 2015, when the Fundão dam collapse caused a mudslide which killed 19 people, destroyed villages and caused widespread environmental damage.

Vale said Samarco was expected to restart using dry tailings stacking.

"For this reason, the operational restart of iron ore extraction and beneficiation plants in Germano and the pelletization plant in the Ubu Complex, located in Anchieta, state of Espírito Santo, will only occur after the implementation of a filtration system, which construction is expected to take approximately 12 months," Vale said.

Initial production was pegged at 7-8 million tonnes per annum.

Vale expected a second concentrator to restart in six years' time to take production to 14-16Mtpa, with a third concentrator likely to restart in 10 years to lift output to 22-24Mtpa.

Samarco's attributable pellet production for Vale in 2014 was 12.1Mt, an annual record.

The joint venture partners had completed a US$3.2 billion expansion project earlier in 2014 which took Samarco's pellet production capacity from 22.3Mtpa to 30.5Mtpa.

In an earnings call last week prior to the licence being announced, Vale CEO Eduardo Bartolomeo said after the fatal Brumadinho tailings dam failure in January, Samarco had to redo its tailing disposal plans.

In the same call, ferrous minerals executive officer Marcello Spinelli said as Samarco did not have tailing disposal systems, it was a big constraint for a full operation restart.

In a translated statement, Samarco said on Friday it continued to analyse and assess the impact of the various regulatory changes in its business plan.

"Samarco anticipates that the current estimate for expenses related to the mischaracterization of the Germano dam and Cava de Germano, which were not being considered in the company's business plan released in January 2019, is approximately R$2.3 billion (~US$0.6 billion)," the company said.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.