Cajueiro set to power on

Canadian microcap Altamira Gold Corp expects to submit plans for a 1.5MW substation to power its proposed 1,000 tonnes per day processing plant at the Cajueiro gold project to the state power utility in Para, Brazil, by the end of August and be in a position to start plant construction in the second half of this year.

Staff reporter
On site at Cajueiro in Para, Brazil

On site at Cajueiro in Para, Brazil

Centrais Eletricas do Para has approved Altamira's recent application to draw power from an existing transmission line which "runs through" Cajueiro's Central resource area, via the substation.

Altamira says the electricity source - obviating the need for onsite diesel generators - will be sufficient to power the processing plant and mine camp facilities.

"The power will be sourced from an existing 34.5kV transmission line originating from the nearby Teles Pires hydro-electric scheme," the company said.

CEO Michael Bennett said "This prompt approval from CELPA secures grid power for the Cajuiero gold project and marks a major step forward in our overall objective of transforming Altamira Gold from an exploration company to a near-term gold producer and will help the company to fast track the plant construction and begin production in 2021 using an environmentally friendly power supply."

Initial engineering and design work on Cajueiro is expected to be completed by the end of July 2020 with Altamira saying a US$1M payment to Metalstream due under their precious metals purchase agreement was expected to be made on July 14.

Altamira is still collecting bulk samples of oxide ore for "further metallurgical evaluation … to ensure that the plant design is optimised for maximum gold recovery" at laboratories in Brazil and Australia. The latter is for CSIRO testwork to "determine whether fine gold in the oxide ore is amenable to recovery using thiosulphate solution which would avoid the requirement for cyanidation".

Cajueiro has NI 43-101 resources of 5.66Mt grading 1.02g/t gold for 185,000oz indicated and 515,000oz inferred.

Altamira Gold Corp (TSXV: ALTA) has a market capitalisation of C$10.4 million at its last trading price of 10c.

 

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.