PROJECT FINANCE

Telson tees up finance to finish Tahuehueto

Telson Mining has finally teed up financing of up to US$25 million to finish construction and ramp-up of its partly-built Tahuehueto gold project in Mexico’s Durango state.

Staff reporter
 The partly-constructed mill at Telson Mining’s Tahuehueto gold project in Mexico

The partly-constructed mill at Telson Mining’s Tahuehueto gold project in Mexico

The company said it was "very pleased" to announce a letter of intent regarding financing with the Accendo syndicate, comprising mining bank Accendo Banco, Empress Royalty and Endeavour Financial.

Accendo would provide a previously-flagged $12 million loan, which was expected to close in March, Empress a $5 million silver stream and the trio along with third parties would arrange a private placement of up to $8 million priced at C20c per unit.

The funds would also help meet debt service obligations and be for working capital purposes.

Telson estimated US$15.4 million was needed to finish construction and commissioning at Tahuehueto, which it said was about 60% complete.

The company said the deal would also allow it to negotiate a potential restructuring of its loan debt with Trafigura and Nyrstar, plus the Accendo syndicate would appoint three new directors and a COO to Telson.

"After many months of extensive hard work and negotiation, I am delighted on behalf of the Telson team to deliver to Telson shareholders and investors this excellent news," president and CEO Ralph Shearing said.

"This funding package now allows Telson to immediately reinitiate construction at the Tahuehueto mine site, after which we expect to rapidly advance construction targeting to commence initial pre-production within 10-12 months and full-scale production 12-14 months after funding."

Telson had hoped to focus on its gold project 18 months ago when it put its base metals Campo Morado mine in Guerrero state on care and maintenance, in August 2019.

However it restarted Campo Morado in January 2020, citing an improvement in the zinc price and community relations.

The operation had since achieved "significant increases" in throughput and concentrate production and benefited from increasing metal prices, with fourth quarter revenues estimated at US$8.7 million.

Tahuehueto was expected to have a 21-year mine life, producing an average annual 16,100 ounces of gold, 177,100oz of silver, 900,000 pounds of copper, 3.2 million pounds of lead and 5.6Mlb of zinc, according to a 2017 prefeasibility study.

Telson shares (TSXV: TSN), which have ranged between C4-32.5c over the past year, shot up 32.5% yesterday to C26.5c to capitalise it at $48.4 million (US$38.4 million).

 

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.