Kerr looks to restart Copperstone in 2019

Junior Kerr Mines (CN:KER) says a positive prefeasibility study for its 600,000 ounce Copperstone gold project in Arizona is “just the beginning” as it aims for production in 2019.

Kerr looks to restart Copperstone in 2019 Kerr looks to restart Copperstone in 2019 Kerr looks to restart Copperstone in 2019 Kerr looks to restart Copperstone in 2019 Kerr looks to restart Copperstone in 2019

Positive PFS points to near-term production

The PFS points to an initial capex of US$22.7 million, thanks to the amount of infrastructure at the past-producing mine, an internal rate of return of 40% and payback within 2.3 years of the fl...