EXPLORATION & DEVELOPMENT

'Powerful' studies point to near-term production at Platreef

Ivanhoe's Platreef joint venture development in South Africa could be in production in mid-2024 according to "powerful" studies released yesterday.

Staff reporter
 Banksman Pierre Kruger and engineering graduate Sipho Monama, members of the Platreef team bringing Shaft 1 safely back into operation, at Ivanhoe’s JV development in South Africa

Banksman Pierre Kruger and engineering graduate Sipho Monama, members of the Platreef team bringing Shaft 1 safely back into operation, at Ivanhoe’s JV development in South Africa

The company released an integrated development plan (IDP), comprising an updated feasibility study on becoming "a world-scale producer of critical ‘green metals'" - and a preliminary economic assessment, which looked at fast-tracking into production using a lower-cost, staged development. 

The updated feasibility study took into account development schedule advancement since 2017, as well as updated costs, metal prices and foreign exchange assumptions; and increased throughput from 4Mtpa to 4.4 Mtpa to use the full processing capacity of two 2.2Mtpa concentrators.

It hinged on developing Shaft 2, targeted first production in 2025 and put initial capex at US$1.4 billion, the after-tax NPV8 at $1.8 billion and IRR at 19.8%, using long-term consensus metal prices.

This changed to an after-tax NPV8 of $3.7 billion and IRR of 28% at spot metal prices.

The updated study forecast average annual production of 508,000oz 3PE+Au, plus 22Mlb of nickel and 13Mlb of copper, at a cash cost of $442/oz 3PE+Au, net of by-products, and including sustaining capital costs.

The PEA however put initial capex at $390 million, to mine near the recently-completed Shaft 1, deferring the Shaft 2 sinking potentially until 2025, and using an initial 770,000tpa capacity concentrator, with first production slated for mid-2024.

It put potential steady state production at an eventual 5.2Mtpa, once the two 2.2Mtpa concentrators were commissioned.

Post-tax NPV8 was $1.6 billion and IRR 20%, for a 30-year mine producing an average annual  109,000oz of platinum, palladium, rhodium and gold (3PE+Au), plus 5 million pounds of nickel and 3Mlb of copper in years one to six, followed by 613,000oz of 3PE+Au, plus 27Mlb nickel and 16Mlb of copper in years 7-30.

The post-tax NPV8 and IRR increased to $3.3 billion and 29% respectively, using spot rather than long-term consensus metal prices.

It envisaged a cash cost of US$460 per ounce of 3PE+Au, net of by-products, and including sustaining capital costs.

Ivanhoe said detailed engineering had begun on the mine design, 770,000tpa concentrator and associated infrastructure for the phased development plan, which would be incorporated into an updated feasibility study in 2021.

The plans envisaged mechanised mining and dry stack tailings storage.

"These powerful, independent economic results mark an important step in our vision of building and operating the world's next great precious metals mine, together with our local community and Japanese partners," co-chairman Robert Friedland said.

"We have a mining licence, we have water, we have an orebody that is as thick as an eight-storey building, and we have a team of highly-skilled employees.

"We also have a 'basket' of precious metals contained in the ore at Platreef that have risen in recent years to levels in excess of $2,100/oz for platinum-group metals and gold."

Ivanhoe owns 64% of Platreef, which it discovered 25 years ago.

"With an attractive first phase of development reflected by the Platreef IDP20, Ivanhoe plans to revisit previous studies dating back to 2014 that have demonstrated the potential for Platreef to support future expansions up to 12Mtpa, producing in excess of 1.1 million ounces of palladium, platinum, rhodium and gold per year," it said.

Bringing Shaft 1 back into operation

Ivanhoe said remedial actions were underway to bring Shaft 1 safely back into operation following a fatal accident in September.

Three people had died and one was injured when a kibble bucket fell down Shaft 1 and struck the northern side of a working platform, where the four were conducting routine water-pumping activities. 

"The Mine Health and Safety Inspectorate has completed its investigation under Section 60 of the Mine Health and Safety Act, and preliminary findings attributed the primary cause of the tragic accident to a very rare electronic device failure and that all mine safety standards and safe operating procedures were fully complied with," Ivanhoe said.

The company is also developing the Kamoa-Kakula copper project and redeveloping the Kipushi polymetallic mine, at separate joint ventures in the Democratic Republic of Congo.

Ivanhoe shares (TSX: IVN) reached a fresh peak of C$6.12 intraday, before closing up 2.5% to $6.08 to capitalise it at $7.3 billion (US$5.6 billion).

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.