BASE METALS

Nouveau bolsters N American graphite plan

Nouveau Monde Graphite has released a feasibility study on its plan of developing a fully integrated source of carbon-neutral battery anode material in Quebec, Canada, which it says will be North America’s largest natural graphite operation.

 Nouveau Monde Graphite, April 2020 webcast

Nouveau Monde Graphite, April 2020 webcast

The results from the study, which comprises the phase 2 Metawinie mine and Becancour Battery Material Plant projects showed an after-tax NPV8% for the integrated model of C$1,581 million (US$1,215 million) and an after-tax IRR of 21%. The after-tax payback period is viewed as 4.2 years.

The after-tax NPV8%, IRR, and payback period for the mine are C$571 million, 22.2%, and 3.7 years, respectively. And for the battery material plant, the metrics stand at C$1,010 million, 20.4%, and 4.5 years.

"NMG is positioning itself as North America's largest, fully integrated natural graphite production to relieve battery and EV manufacturers from their overreliance on Chinese production," NMG's founder, president, and CEO Eric Desaulniers said.

The initial capital expenditure for the integrated project is set at C$1,404 million, which is made up of C$481 million for the mine and C$923 million for the battery material plant. The annual operating expenditure is viewed as C$195 million, with the mine accounting for C$58 million, and the plant C$136 million.

The mine's average annual production is viewed as 103,328 tonnes of graphite concentrate, and the plant is set to see 42,616 tonnes of anode material, 3,007 tonnes of purified jumbo flakes, and 18,384 tonnes of by-product fines.

The life of mine is 25 years.

"The successful upstream integration is designed to ensure that we have access to high-quality, responsible feedstock for decades to come, and provides battery and EV manufacturers with the assurance of a traceable, local, and carbon-neutral supply," NMG's chair Arne Frandsen said.

NMG said that the study has shown that the projects are technically feasible as well as economically viable, which will strengthen its ongoing finance efforts.

Once a final investment decision is made, the phase 2 Matawinie mine and Becancour plant could be built within about a 30-month schedule, the company said.

NMG's share price fell 6% day on day to C$6.20 on July 6. The company has a market capitalization of C$345.61 million.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.