NexGen's Rook I EIS progresses

NexGen's EIS for Rook I moves into next phase

 NexGen Energy's Rook I project

NexGen Energy's Rook I project

"In our view, this is a major permitting milestone which focuses on the ESG aspect of project development. It included indigenous and community engagement, incorporated best environmental practices, and was transparent in engaging with regulators and governments," Red Cloud Securities said.

"Rook 1 is one of the largest development stage uranium projects in Canada," it added.

A 2021 feasibility study on the project viewed a 1,300 tonnes per day operation, with an average annual production for years 1-5 of 28.8 million pounds U3O8 and a life of mine of 10.7 years.

With total pre-production capital costs expected at C$1,300 million (US$1,003), the study viewed an after-tax NPV8% of C$3.47 billion and after-tax IRR of 52.4%.

"Other near-term catalysts for the stock include 1) completion of the Front-End Engineering Design (FEED) stage of the project, and 2) commence detailed engineering in H2/22," Red Could noted.

NexGen's share price on July 18 was C$4.91. The company had a market capitalization of C$2.35 billion.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Journal Intelligence team.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across...

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on quarterly mining...

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices...

editions

Mining Journal Intelligence Project Pipeline Handbook 2023

View our 50 top-ranked mining projects, handpicked...