Bluestone publishes Cerro Blanco FS

Bluestone Resources (TSXV:BSR) has outlined a 112,000-ounce per annum mine plan for the Cerro Blanco project in Guatemala, which it hopes to finance in the next six months.

Bluestone's $196 million Cerro Blanco gold project in Guatemala to produce 112,000ozpa

Bluestone's $196 million Cerro Blanco gold project in Guatemala to produce 112,000ozpa

The study details an eight-year mine life with 146,000ozpa production in the first three years at an all-in sustaining cost of US$579 per ounce, putting Cerro Blanco in the lowest quartile of the global cost curve.

With an initial capital investment of $196 million the project yields an after-tax internal rate of return of 34% and after-tax net present value of $241 million based on a $1,250/oz gold price and $18/oz silver price.

"We acquired the project barely 18 months ago so we have done a lot of work in a very short time," president and CEO Darren Klinck told Mining Journal.

"The feasibility demonstrates a leading gold development project that already has its exploitation license, and it will generate more cash flow in its first year of production than our current market cap." 

The project has proven and probable mineral reserves of 940,000oz of gold and 3.6Moz of silver (3.4Mt grading 8.5g/t gold and 32.2g/t silver).

The study excludes an additional 357,000oz of inferred resources (1.4Mt grading 8.1g/t gold and 23.6g/t silver).

Bluestone will advance to project financing over the next six months while continuing to optimise the project.

The company said optimisation possibilities included mine life extension through upgrading some of the 360,000oz of inferred resources to measured and indicated through infill drilling, potential resource growth from step-out drilling along existing veins, the identification of new high-grade veins during infill drilling, finding alternatives to paste fill and use of ore sorting technology.

The study is based on a 1,250 tonnes per day plant with three-stage crushing and two-stage ball mill grinding.

The flowsheet includes pre-oxidation, a 48-hour leach circuit, followed by a six-hour carbon-in-pulp adsorption circuit with expected recoveries of 96% gold and 85% silver.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.