PRECIOUS METALS

Alacer's 'monumental' Copler milestone

First sulphide ore being processed as plant ramps up to nameplate capacity

Staff Reporter

This article is 7 years old. Images might not display.

The Toronto-based company said the first autoclave came on line over the weekend and was now operating as designed.

The sulphide plant was completed 11% under budget at US$673 million and the company had previously guided for 2018 production from the sulphide circuit ranging between 50,000-100,000oz.

Commercial production is expected in early 2019 and the ramp up to full nameplate capacity of 1.9 million tonnes per year will be achieved by the end of 2019, according to the company.

"The successful processing of sulphide ore represents a monumental milestone for Alacer and all of its stakeholders. We can now confidently say the Çöpler mine will deliver tremendous value for many years to come," CEO Rod Antal said.

The oxide plant continued to operate and the company had previously increased the full-year guidance to 110,000-130,000oz, at all-in sustaining costs ranging between $650-$700/oz.

The company's equity has eked out a near-9% increase over the past 12 months but traded about 0.5% lower Tuesday at C$2.21, which gave the company a market value of $647.92 million.

 

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Leadership Insights 2025

Leadership Insights reveals key trends in priority mining issues through interviews with 15+ top mining company executives and an industrywide survey.

editions

Mining IQ Risk Analytics

Risk Analytics offers interactive access to World Risk Insight data, allowing you to customise risk views, benchmark jurisdictions, explore data behind scores and read expert commentary to guide your decision-making.

editions

Project Pipeline Index 2025

View our 50 top mining projects, handpicked using a unique, objective selection process from an expanded database of 600+ global assets.