Minera touts Cerro de Oro PEA as 'game changer'

The PEA includes an after-tax IRR of 111% and NPV5% of US$150.5 million

This article is 3 years old. Images might not display.

The PEA sees an after-tax NPV5% of US$150.5 million, pre-production capital costs of $28.1 million, and a payback period of 11 months, the company said.

"Leaning on our team's collective experience in mine building in Mexico with capital and operating costs informed by the recent construction and ramp up of the Santana gold mine, the Cerro do Oro PEA is a game changer for Minera as we strive to reach our initial target of a +100,000 ounce/year gold producer," Ramshaw said.

The average annual gold production is projected to be about 60,000oz to 70,000oz in years one through four, with an 8.2 year mine life.

The LOM all-in sustaining cost is set at $873/oz - averaging $763/oz in the first four years.

The Mexico-focused company produced its first gold in October 2021. Its portfolio includes the Santana open-pit, heap-leach mine in Sonora, which is going through an operational ramp-up, and the La Fortuna open pit project in Durango - along with Cerro do Oro in Zacatecas.

Minera's share price climbed 13% day on day to more than a three-month high of C$0.54 (US$0.40) on 4 October. The company has a market capitalisation of C$242.05 million.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

Expert-led Insights reports and Analytics tools built on robust data, rigorous analysis and expert commentary covering mining Risk, Projects, ESG, Leadership, and Investor Sentiment.

editions

Leadership Insights 2025

Leadership Insights reveals key trends in priority mining issues through interviews with 15+ top mining company executives and an industrywide survey.

editions

Mining IQ Risk Analytics

Risk Analytics offers interactive access to World Risk Insight data, allowing you to customise risk views, benchmark jurisdictions, explore data behind scores and read expert commentary to guide your decision-making.

editions

Project Pipeline Index 2025

View our 50 top mining projects, handpicked using a unique, objective selection process from an expanded database of 600+ global assets.

editions

Investor Sentiment Insights 2025

Exclusive insights into the plans, priorities and preferences of 130+ mining investors and top factors influencing investment decisions in 2025.